NEW QUESTION 68
You are the Scrum Master ofthe JKM Project and your Development Team has asked to change some rules about the duration of the Sprints. Which one of the following statements is a rule of Scrum that the team should follow when it comes to Sprint duration?
- A. The Sprint duration should not change once the project begins.
- B. Multiple Scrum teams, in one project, can start their Sprints as soon as the Development Team is assembled.
- C. Multiple Scrum teams can have sprints of different duration in one project.
- D. When possible, Sprints should start on a Tuesday rather than a Monday.
Answer: A
NEW QUESTION 69
Maria is one of the Scrum Master for a rail-road reservation system program. She facilitates the Daily Standup Meetings to enable the Scrum Team to discuss issues faced by individual members, and seek solutions to motivate the team. Which of the following represents the mandatory outputs of Conduct Daily Standup process?
- A. Updated Scrumboard and Dependencies.
- B. Updated Sprint Burndown chart and Impediment log.
- C. Updated Sprint Burndown chart and Motivated Scrum Team.
- D. Updated Scrumboard and Unapproved Change Requests.
Answer: B
Explanation:
Reference:
http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf (62)
NEW QUESTION 70
Listed below are some responsibilities of a Scrum Master. Identify the one that is NOT correct.
- A. Resolves the issues affecting the Scrum Team.
- B. Coordinates with Product Owner in creation of the Prioritized Product Backlog.
- C. Facilitates Prioritized Product Backlog Review Meetings.
- D. Identifies risks and implements risk mitigation actions.
Answer: B
NEW QUESTION 71
You are the Scrum Master for your organization and you are working to create a Development Team. Which one of the following is the best solution to create a Development Team for a new project?
- A. Have the Development Team work directly the customers of theproject.
- B. Hire a Scrum Coach to help the developers become self-managing.
- C. You should allow the developers to self-organize into a Development Team.
- D. Recruit people from departments within theorganization that can best support the project.
Answer: C
NEW QUESTION 72
As a Scrum Master, it is important that you assess skill gapsand training requirements for the team members, and map the skills, capabilities, and interest level of team members in using those skills and capabilities on a project. Which one of the following tools can help you do this?
- A. Organizational Deployment Method.
- B. Organizational Resource Matrix.
- C. Daily Standup.
- D. Skills Requirement Matrix.
Answer: D
Explanation:
Explanation
The Skills Requirement Matrix, also known as a competency framework, is used to assess skill gaps and training requirements for team members. A skillsmatrix maps the skills, capabilities, and interest level of team members in using those skills and capabilities on a project. Using this matrix, the organization can assess any skill gaps in team members and identify the employees who will need further training in a particular area or competency. Team members may not always possess the required knowledge or skills to work in the Scrum environment. The Product Owner should evaluate the training needs of potential team members and facilitate training tobridge any knowledge gaps in the team.
NEW QUESTION 73
Which of the following methods helps estimate the value provided by projects?
- A. Estimated Rate of Return
- B. Net Rate of Return
- C. Internal Rate of Return
- D. Present Rate of Return
Answer: C
Explanation:
Explanation
The value to be provided by business projects can be estimated using various methods such as Return on Investment (ROI), Net Present Value (NPV) and Internal Rate of Return (IRR).
NEW QUESTION 74
Gregory is the Scrum Master on a project to create automated devices for the health industry. He advocates that every member of the Scrum Team should actively participate in team building activities, estimation meetings, and in Daily Standups. He looks to give more responsibility to team members. Which of the following theories does Gregory seem to subscribe to?
- A. Theory X
- B. Maslow's hierarchy of needs
- C. Win/Win Conflict Resolution
- D. Theory Y
Answer: B
Explanation:
Explanation/Reference: https://medium.com/serious-scrum/we-dont-let-the-teams-self-organise-fd27807d8e15
NEW QUESTION 75
All of the following statements about Risk Communications are true, EXCEPT:
- A. The Stakeholders should be continuously informed about risks, including the potential impact of these risks and the plans for responding to each risk.
- B. The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to the Scrum Team.
- C. Information related to risks is maintained and updated through the Risk Burndown Chart.
- D. The Scrum Team may also discuss specific risks related to their Tasks with the Product Owner during Daily Standup Meetings.
Answer: D
Explanation:
Because stakeholders have an interest in the project, it is important to communicate with them regarding risks.
Information provided to stakeholders related to risk should include potential impact and the plans for responding to each risk. This communication is on-going and should occur in parallel with the four sequential steps discussed thus far-risk identification, assessment, prioritization and mitigation. The Scrum Team may also discuss specific risks related to their Tasks with the Scrum Master during Daily Standup Meetings. The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to the Scrum Team. An important tool which can be used for communicating information related to risks is the Risk Burndown Chart.
NEW QUESTION 76
Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?
- A. Eliminating all changes that may affect the quality of deliverables and processes
- B. Facilitating identification of Change Requests by the Scrum Team and their assessment and prioritization by the Product Owner.
- C. Providing requests for changes in a project.
- D. Approving changes that are amended, removed, or added according to project requirements, and communicating the same to the Scrum Team.
Answer: B
NEW QUESTION 77
Scrum Masters have to solve both internal and external impediments for the Scrum team during the Create Deliverables process. To do so, they record the impediments in the Impediment Log during
_________________________.
A) Daily Standup Meetings.
B) Sprint Review Meetings.
C) Release Planning Meetings.
D) Sprint Planning Meetings.
- A. A and D
- B. A
- C. A, B, and C
- D. A and B
Answer: D
Explanation:
Explanation/Reference: http://www.cs.vsu.ru/~svv/spm/SBOK_Guide_3rd_edition_English_Sample.pdf (45)
NEW QUESTION 78
A large software company has 8 Scrum teams with each team having a Scrum Master. After the Daily Standup everyday with their respective teams, all Scrum Masters meet for a Scrum of Scrums. What are they likely to do during this meeting?
- A. Discuss what each individual development team member has worked on since the last time all Scrum Masters met.
- B. Share a status update on all individual team member' tasks.
- C. Discuss actions of a team that could potentially affect another team.
- D. Discuss ways to resolve technical impediments faced by development teams, especially if two or more teams face the same issue.
Answer: D
NEW QUESTION 79
Which of the following is a tool that can be used for communicating information related to risks?
- A. Risk Progress chart.
- B. Risk Tracking chart.
- C. Risk Burndown chart.
- D. Risk Burnup chart.
Answer: C
Explanation:
An important tool which can be used for communicating information related to risks is the Risk Burndown Chart.
NEW QUESTION 80
Collaboration is one of the Scrum principles. Which of the following are the three dimensions of this principle?
- A. Transparency, precision, and coordination
- B. Honesty, responsiveness, and adaptability
- C. Perfection, cooperation, and comprehension
- D. Awareness, articulation, and appropriation
Answer: D
Explanation:
Explanation
The core dimensions of collaborative work are as follows:
1.Awareness - Individuals working together need to be aware of each other's work.
2. Articulation - Collaborating individuals must partition work into units, divide the units among team members, and then after the work is done, reintegrate it.
3. Appropriation - Adapting technology to one's own situation; the technology may be used in a manner completely different than expected by the designers.
NEW QUESTION 81
Scrum is best described as a
- A. Collection of best practices
- B. Product development process
- C. Framework for developing and sustaining complex products
- D. Software methodology
Answer: C
NEW QUESTION 82
Suppose you are a Scrum Master or a Scrum Team that is progressing through Tuckman's model of Group Dynamics. In which of the following stages will you be most actively involved?
- A. Performing
- B. Norming
- C. Forming
- D. Storming
Answer: C
NEW QUESTION 83
The Scrum Team along with the Scrum Master adopted the Fist of Five technique to arrive at accurate estimations for the prioritized User Stories. The results of the vote of each team member are as follows:
three members: 2 fingers; four members: 3 fingers; and two members: 5 fingers. Which of the following options is in plurality?
- A. I wholeheartedly agree with the group's conclusion.
- B. I agree with the group's conclusion and would like to discuss some minor issues.
- C. I am not sure and would like to go with the group's consensus conclusion.
- D. I disagree with the group's conclusion and have major concerns.
Answer: D
Explanation:
Explanation/Reference: https://ryanripley.com/5-reasons-a-scrum-master-should-use-fist-of-five-voting/
NEW QUESTION 84
As a Scrum Master you should be familiar with all roles and responsibilities of a Scrum Project Which role can also be described as a Value Optimizer for the project?
- A. Development Team
- B. Product Owner
- C. Scrum Master lite
- D. Scrum Master
Answer: B
NEW QUESTION 85
The Scrum Team along with the Scrum Master adopted the Fist of Five technique to arrive at accurate estimations for the prioritized User Stories. The results of the vote of each team member are as follows: three members: 2 fingers; four members: 3 fingers; and two members: 5 fingers. Which of the following options is in plurality?
- A. I am not sure and would like to go with the group's consensus conclusion.
- B. I wholeheartedly agree with the group's conclusion.
- C. I agree with the group's conclusion and would like to discuss some minor issues.
- D. I disagree with the group's conclusion and have major concerns.
Answer: A
NEW QUESTION 86
You are the Scrum Master for a project in a new Scrum environment. The Development Team is confused about their responsibilities in a Sprint. Of the following which one is not part of the Development Team's responsibilities?
- A. The Development Team willestimate the work of Product Backlog.
- B. The Development Team will consult on user stories for the Product Backlog.
- C. The Development Team chooses the Product Owner for each Sprint.
- D. The Development Team determines who'll do what task in the Sprint Backlog.
Answer: C
NEW QUESTION 87
Scrum effectively limits the risk of unknowingly doing something wrong by
- A. Having a detailed and extensive risk management plan
- B. Having multiple checkpoints and a thorough review by seniormanagement at those checkpoints
- C. Using short iterations called Sprints
Answer: C
NEW QUESTION 88
The Chief Scrum Master facilitates the Scrum of Scrums Meeting. Which of the following statements about a Scrum of Scrums Meeting is true?
- A. This meeting is always time-boxed.
- B. This meeting can be scaled up.
- C. This meeting can be conducted at any time without any pre-determined intervals.
- D. This meeting is relevant only for high-investment projects.
Answer: B
Explanation:
Explanation
Explanation/Reference: https://www.smartsheet.com/blog/5-stages-creating-successful-scrum-scrums#the-importance- of-project-management-soft-skills-in-scrum-of-scrums
NEW QUESTION 89
Which of the following statement(s) is/are true with respect to Change in Scrum projects?
A) The Scrum Master suggests changes in consultation with the Scrum Team.
B) The Scrum Master can recommend changes based on Retrospect Sprint Meetings.
C) Changes that are beyond the tolerance level of the Product Owner may need the assistance of the Scrum Master working with the Product Owner.
D) The Scrum Master finalizes the formal change requests along with the Scrum Team.
- A. C and D
- B. Only D
- C. Only A
- D. A and B
Answer: A
NEW QUESTION 90
......
How much Scrum Master Certified (SMC) Exam Cost
The cost of the Scrum Master Certified (SMC) Exam is $450 USD. For more information related to exam price, please visit the official website at SCRUMstudy Website as the cost of exams may vary according to the region of the candidate.
100% Free SMC Daily Practice Exam With 149 Questions: https://www.examslabs.com/Scrum/Scrum-Certified/best-SMC-exam-dumps.html
Pass SMC Review Guide, Reliable SMC Test Engine: https://drive.google.com/open?id=161VP2c_niqSk2FftozKzpS4ld1-2fxHa