AACE International is a globally recognized authority in project management, cost engineering, and controls. The AACE-PSP Certification Exam is an industry-recognized certification that validates the skills and knowledge of professionals in project planning and scheduling. Planning & Scheduling Professional (PSP) Exam certification is designed to assess the proficiency of professionals in project planning and scheduling by testing their ability to apply the best practices and techniques in project management.
AACE International is a globally recognized professional association for the management and development of cost and schedule professionals. The organization provides a variety of professional certifications, including the AACE-PSP (Planning & Scheduling Professional) certification, designed for professionals who specialize in project scheduling, planning, and control.
NEW QUESTION # 88
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
- A. 3 cranes
- B. 4 cranes
- C. 2 cranes
- D. 1 crane
Answer: C
NEW QUESTION # 89
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
- A. 12-18-03 and 25 days of float
- B. 12-17-03 and 4 days of float
- C. 12-27-03 and 24 days of float
- D. 12-18-03 and 4 days of float
Answer: B
NEW QUESTION # 90
Identify the late finish to develop plans and specs.
- A. 8 months.
- B. 9 months.
- C. 10 months.
- D. 7 months.
Answer: B
NEW QUESTION # 91
Project delays are best analyzed
- A. By an expert after the project is finished when complete records are available and the impact is known.
- B. Late in the project.
- C. After either the contractor or the owner acknowledges ^responsibility for the delay.
- D. Contemporaneously with the delay.
Answer: A
NEW QUESTION # 92
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 267 days
- B. 407 days
- C. 362 days
- D. 255 days
Answer: B
NEW QUESTION # 93
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?
- A. 37.
- B. 36.
- C. 40.
- D. 42.
Answer: B
NEW QUESTION # 94
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. The schedule is projecting an "early completion".
- B. Different calendars are assigned to certain activities in the logical chain.
- C. Certain activities in the critical path have no successors.
- D. The schedule has too much detail to reflect an accurate critical path.
Answer: C
NEW QUESTION # 95
Determine the correct formula and date for the late finish for Activity 9004.
- A. LS.10002^ Lag.7 + i day -> 11-20-03.
- B. LS.10002 - Lag.7 - l day -> 11-20-03.
- C. LS.10002 - 1 day -> 11-27-03.
- D. LS.10002 + 1 day -> 11-29-03.
Answer: A
NEW QUESTION # 96
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
- A. 3.9% (1 : 25.708)
- B. 9.1% (1 : 11.000).
- C. 8.6% (1 : 11.591)
- D. 2.3% (1 : 43.501).
Answer: D
NEW QUESTION # 97
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?
- A. 2003 and 7001
- B. 2004, 4001. and 5001
- C. 4001, 5001, and 6001
- D. 4001 and 5001
Answer: C
NEW QUESTION # 98
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?
- A. Drafting and Proofing the Manual.
- B. Testing, Manufacturing and Packaging.
- C. Printing the Manual.
- D. Packaging only.
Answer: B
NEW QUESTION # 99
What changes to logic would eliminate Activity B from the critical path?
- A. Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0
- B. Replace the relationship from Activity B to Activity C with SSO
- C. Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C
- D. Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO
Answer: C
NEW QUESTION # 100
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
- A. Predecessor is activity 4001, successor is activity 8001
- B. Predecessor is activity 9001, successor is activity 9002
- C. Predecessor is activity 5001, successor is activity 8001
- D. Predecessor is activity 5001, successor is activity 8002
Answer: C
NEW QUESTION # 101
What is the relationship depicted between Activity G and Activity H?
- A. Finish-to-start.
- B. You cannot tell with the supplied information.
- C. Finish-to-finish.
- D. Start-to-start.
Answer: D
NEW QUESTION # 102
Is activity 7001 pictured correctly in the precedence diagram?
- A. No, the total float is not shown correctly.
- B. Yes, except the early finish date is not shown.
- C. No, the start-to-start and finish-to-finish relationships are backwards.
- D. Yes, the duration is 48 days.
Answer: D
NEW QUESTION # 103
......