
2023 Latest C_IBP_2211 DUMPS Q&As with Explanations Verified & Correct Answers
C_IBP_2211 dumps Exam Material with 80 Questions
SAP C_IBP_2211 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
NEW QUESTION 35
What do you need to be aware of when using multiple pairs of key figures in one copy operator? Note:
There are 2 correct answers to this question.
- A. Copying multiple key figures on different planning levels is not possible.
- B. Copying multiple key figures can be processed sequentially.
- C. If necessary target key figures values are disaggregated.
- D. If necessary source key figures values are disaggregated.
Answer: B,C
NEW QUESTION 36
Using the import/export functionality means working with groups of items that are organized into collections.What is the best practice for managing collections?
- A. You should delete collections after they have been transported.
- B. Configuration items should be bundled in the collections based on the SAP IBP project stream.
- C. A planning area with its time profile must be bundled in one collection.
- D. A planning area with the copy operators assigned must be bundled in one collection.
Answer: C,D
NEW QUESTION 37
Which constraints are taken into account by the Time-Series-Based Supply Planning Heuristic (Infinite)?Note: There are 3 correct answers to this question.
- A. Transportation lead times
- B. Adjusted transport receipts
- C. Minimum lot size
- D. Aggregated constraints
- E. Maximum lot size
Answer: A,B,E
NEW QUESTION 38
What function would you use to configure a year-to-date calculation?
- A. Rolling Aggregation
- B. Dynamic Rolling Aggregation
- C. Cumulative Aggregation
- D. Last Period Aggregation
Answer: C
NEW QUESTION 39
Which of the following key functions are supported by SAP IBP for sales and operations?Note: There are 2 correct answers to this question.
- A. Simple statistical forecast
- B. Multi-Level Supply Planning Heuristics
- C. Scenario analysis for operational supply planning
- D. Time series analysis
Answer: A,B
NEW QUESTION 40
Which of the following key functions are supported by SAP IBP for sales and operations?Note: There are
2 correct answers to this question.
- A. Simple statistical forecast
- B. Multi-Level Supply Planning Heuristics
- C. Scenario analysis for operational supply planning
- D. Time series analysis
Answer: A,B
NEW QUESTION 41
You need to define a new logic for a key figure to drive values from the PERPRODCUSTREGION level to the PERPRODCUST level.Which of the following configuration options are possible for this process?Note: There are 2 correct answers to this question.
- A. Splitting the values from aggregated to detailed level using multiplication by the proportions
- B. Splitting the values from aggregated to detailed level, based on the time profile attribute
- C. Splitting the values from detailed to aggregated level by using a copy operator
- D. Splitting the values from aggregated to detailed level, based on a stored split-factor key figure
Answer: A,D
NEW QUESTION 42
You need to create time periods for the time profile in a planning area.What should you be aware of when running the Create Time Periods application job?
- A. This application job can be run for multiple time profiles at once.
- B. A time profile has to be activated so that the application job can proceed.
- C. The assigned Planning Area must be active.
- D. In the Parameter Section of the application job, choose the Time Profile ID and Planning Area.
Answer: D
NEW QUESTION 43
You define fixing for a key figure.Which of the following functions are available for this key figure? Note: There are 2 correct answers to this question.
- A. Fixing is possible for a certain quantity of a key figure value.
- B. Fixing is possible for system editable key figures.
- C. Fixing is possible for a certain period, including all child values in the hierarchy.
- D. Fixing is possible for manually editable key figures.
Answer: B,C
NEW QUESTION 44
Which type of Master Data will be represented by the Master Data Type LOCATIONFR?
- A. Reference Master Data Type
- B. Compound Master Data Type
- C. Virtual Master Data Type
- D. External Master Data Type
Answer: A
NEW QUESTION 45
What are some of the prerequisites for configuring a planning area that results in a successful consistency check?Note: There are 2 correct answers to this question.
- A. Specify a planning horizon in the planning area for each level of the assigned time profile.
- B. Configure at least one calculated key figure for the planning area.
- C. Assign the compound master data type and its component master data types.
- D. Configure at most two input key figures on the same planning level in a key figure calculation.
Answer: A,C
NEW QUESTION 46
Which conditions have to be fulfilled as a prerequisite to maintain a key figure disaggregation?Note: There are 2 correct answers to this question.
- A. The key figure is stored and all editable.
- B. The key figure is calculated and system editable.
- C. The key figure is calculated and all editable.
- D. The key figure is stored and system editable.
Answer: A
NEW QUESTION 47
For which of the following application jobs can you enter planning filters as parameters?Note: There are 2 correct answers to this question.
- A. Purge Master Data
- B. Purge Non-Conforming Data
- C. Create Time Periods for Time Profiles
- D. Purge Key Figure Data
Answer: A,D
NEW QUESTION 48
A time profile is defined with these levels: day, technical week, week, month, quarter, and year. What condition in configuration will allow you to have a different value in the current week, versus all other time buckets?
- A. IF("PERIODID5" ="$$PERIODID5CU$$...)
- B. IF("PERIODID4" ="$$PERIODID4CU$$...)
- C. IF("PERIODID3" ="$$PERIODID3CU$$...)
- D. IF("PERIODID2" ="$$PERIODID2CU$$...)
Answer: B
NEW QUESTION 49
You want to display and edit data in different Units of Measure (UOM).Which of the following must you consider before you use the UOM?Note: There are 3 correct answers to this question.
- A. Units of measure are usually not time-independent.
- B. Unit of measure is an attribute of a master data type, such as Product.
- C. Units of measure are usually not time-dependent.
- D. Conversion to the target unit of measure is handled by SAP IBP Excel UI
- E. Analytics provide the user with the option to select the target unit of measure.
Answer: B,C,E
NEW QUESTION 50
What does ABC/XYZ segmentation allow you to do?Note: There are 2 correct answers to this question.
- A. Choose time-independent key figures as segmentation measures.
- B. Substitute missing values in case of sporadic demands.
- C. Identify inventory items that require closer attention.
- D. Use forecasting algorithms that are specific to seasonal demands of SKUs in the segment "B".
Answer: A,C
NEW QUESTION 51
You are modeling a new product introduction.Which of the following steps can be part of your modeling process in the Manage Product Lifecycle app?Note: There are 2 correct answers to this question.
- A. Copy the launch dimension from the reference product to the new product
- B. Create planning objects for new combinations in the app
- C. Enter the Phase-out Start Date and Phase-out End Date
- D. Enter the product family to which the new product belongs
Answer: A,B
NEW QUESTION 52
You are starting a new implementation project for SAP IBP and are considering the possible system architecture.What are the possible approaches for setting up the system landscape?Note: There are 2 correct answers to this question.
- A. Create additional planning areas in the test system to support training needs.
- B. Create additional test planning areas in the production system to support cutover needs.
- C. Set up a two-tier landscape, and have the configuration of the development system regularly updated from the production system.
- D. Set up a three-tier landscape using transport, starting from the development system to test and production.
Answer: C,D
NEW QUESTION 53
Which of the following are functions of SAP IBP for demand?Note: There are 2 correct answers to this question.
- A. Detailed statistical analysis of demand data using predictive analytics tools
- B. Embedded, on-the-fly demand analytics
- C. Demand sensing of demand data using predictive analytics tools
- D. Consideration of demand-driven analysis for buffer positioning.
Answer: A,B
NEW QUESTION 54
You need to make manual adjustments to your S&OP plan.Which are possible ways of making these changes?Note: There are 2 correct answers to this question.
- A. Leveraging the web-based planning capability
- B. Leveraging the functionality of SAP Workzone
- C. Using Microsoft Excel planning views
- D. Using Driver-Based planning
Answer: A,C
NEW QUESTION 55
......
Share Latest C_IBP_2211 DUMP Questions and Answers: https://www.examslabs.com/SAP/SAP-Certified-Application-Associate/best-C_IBP_2211-exam-dumps.html
C_IBP_2211 Questions and Answers Guarantee you Oass the Test Easily: https://drive.google.com/open?id=13eTri7bcSFf9uxo5R7L11T4hS-jABpz7