SAP Certified Application Associate - Quality Management with SAP ERP 6.0 EHP5 - C-TPLM40-65 Exam Practice Test
Which QM master data must you maintain to separate a sample into a primary and reserve sample?
Correct Answer: C
You create a supplier claim notification with reference to material document year, number and item from a goods receipt for the PO. What information is copied to the notification? Note : 3 correct answer
Correct Answer: A,B,C
What master data can you integrate into a task list for a production order?
Correct Answer: B
After you create customer master records, you define second inspection related default specification in the ....
Which of the followings options can you use to control when the quality inspection take place (2 correct ans)
Which of the followings options can you use to control when the quality inspection take place (2 correct ans)
Correct Answer: A,D
How does the system handle equipment and functional locations in an inspection lot in calibration inspection?
Correct Answer: B
Which inspection origin creates only unplanned physical samples?
Correct Answer: C
Which process step can automatically create a quality notification?
Correct Answer: A
When creating a process order , what type of task list is primary used for inspection ? Correct 3
Correct Answer: A,C,D
Your customer user action boxes in the notification processing and wants relationships to exist between the different In which implementation guide activity do you define these relationships ?
Correct Answer: B