SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4 - C-TPLM22-64 Exam Practice Test
Which type of down-payment chain allows you to monitor receivables to customers and to gain information on past and future incoming payments?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?
Please choose the correct answer.
Response:
Capacity planning board
Please choose the correct answer.
Response:
Capacity planning board
Correct Answer: B
How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement or fully responsible for procurement?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
How can material components be assigned to network activities?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,E
How do you evaluate and display details of orders and networks that create capacityrequirements at the work centers?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
If the available user-definable fields do not satisfy your requirement, you have an option to develop additional fields for which of the following.
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,B
How can the capacity requirements of an activity be reduced?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,D
In Structure Information System which transactions allow you to analyze and edit the entire hierarchical structure of a project including documents, PS texts, networks, other orders, investment programs, and SD documents?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
What are the different views available for capacity planning and work center planning?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,D
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Could a user with Access Control List (ACL) authorization 'Read' lock a project?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,D
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C