A utility company sees several 'New Connect' activities being added to the routing bucket throughout the day.
They want 'Meter Read' activities to potentially be removed from the technician's route so that the 'New Connect' activities can be assigned if the technician qualifies for the activity.
They enabled reoptimization in their routing plan and created a reoptimization filter targeting the 'Meter Read' activities.
What additional settings are required in the routing plan to meet the desired behavior?
They want 'Meter Read' activities to potentially be removed from the technician's route so that the 'New Connect' activities can be assigned if the technician qualifies for the activity.
They enabled reoptimization in their routing plan and created a reoptimization filter targeting the 'Meter Read' activities.
What additional settings are required in the routing plan to meet the desired behavior?
Correct Answer: D
Which two statements are true regarding managing inventory in OFSC?
Correct Answer: B,C
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
Your customer noticed a message that sometimes appears when they are moving activities between resources.
The message reads "Soft skill mismatch" and the customer wants it changed to read "Resource does not meet Preferable work skill level".
Which option fulfills that requirement?
The message reads "Soft skill mismatch" and the customer wants it changed to read "Resource does not meet Preferable work skill level".
Which option fulfills that requirement?
Correct Answer: A
While most field resources for a particular company should see the countdown that displays the estimated time remaining for an activity in Oracle Field Service Cloud (OFSC), their 'contractor resources' that only perform periodica work should NOT see it.
Which configuration supports the requirement to hide the countdown timer for those 'contractor resources' that do NOT need to see it when they are working on their assigned activities?
Which configuration supports the requirement to hide the countdown timer for those 'contractor resources' that do NOT need to see it when they are working on their assigned activities?
Correct Answer: B
Identify three examples of how filters are utilized within Oracle Field Service Cloud.
Correct Answer: A,B,E
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
Where are permissions enabled for users to access Collaboration?
Correct Answer: C
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
Which two customer requirements are solved using work skills?
Correct Answer: C,D
Your customer wants to integrate OFSC with Oracle Knowledge Advanced Cloud.
What are the two main steps that must be taken as part of the integration process to allow Oracle Knowledge Advanced Cloud content to be accessed from the OFSC application?
What are the two main steps that must be taken as part of the integration process to allow Oracle Knowledge Advanced Cloud content to be accessed from the OFSC application?
Correct Answer: A,E
You have a customer located on the east coast of the US (UTC -5hr, assuming Standard Time). Smart Location stores the times from incoming coordinates in UTC.
To ensure that an external system sending the coordinates addresses the offset between the local time and UTC, which <time> element within a Smart Location API "set_position" request would be correct?
To ensure that an external system sending the coordinates addresses the offset between the local time and UTC, which <time> element within a Smart Location API "set_position" request would be correct?
Correct Answer: A