SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager - E_ACTCLD_23 Exam Practice Test

Which of the following building blocks are part of the SAP S/4HANA platform? There are 2 answers to this question.
Correct Answer: A,D
Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 answers to this question.
Correct Answer: A,D
What are the enablement areas relevant for all Customer Team members coming from the Business?
Correct Answer: A,B,D
Which of the following are part od the 10 SAP Quality Principles? 2 correct answers
Correct Answer: B,D
Which end-to-end turn-key application lifecycle management (ALM) solution can support You in managing requirements and software development for large Agile project.
Correct Answer: B
What are some of the key topics covered in the Customer Team Enablement workstream? 3 correct answers
Correct Answer: B,C,D
Which of the following adoption approaches are used in the ERP Implementation Strategies?
Correct Answer: A,D
Where can you check for the current roadmap of SAP Cloud ALM?
Correct Answer: A
What can you do in the SAP Roadmap Viewer tool?
Correct Answer: B
In which tools can the project team across the SAP Activate Methodology content including accelerators?
There are 2 answers to this question.
Correct Answer: A,C