SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP6 - C_TSCM42_66 Exam Practice Test

What data can be posted directly via the Plant Data Collection (PP-PDC) interface?
Correct Answer: C
What do you have to consider regarding consumption?(Choose two)
Correct Answer: A,C
During the processing of production orders planned and actual costs are determined.
On which of the following objects can you collect these costs?(Choose two)
Correct Answer: A,C
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
Correct Answer: B
You want to reduce the uncertainty caused by fluctuating requirements for a finished product by using a dynamic safety stock in SAP ECC.
On which specifications is the dynamic safety stock calculation based?
Correct Answer: B
Which of the following scheduling types can only be used in capacity planning?
Correct Answer: D
Where can you define the valid receivers for production order costs?
Correct Answer: D
Which of the following requirements is supported by using process orders?
Correct Answer: B