SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP5 - C_TSCM42_65 Exam Practice Test

Which of the following requirements is supported by using process orders?
Correct Answer: B
During the processing of production orders planned and actual costs are determined.
On which of the following objects can you collect these costs? (Choose two)
Correct Answer: A,C
Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.
Which BOM item category must you set to fulfill this requirement?
Correct Answer: D
Which of the following statements about consumption are correct? (Choose two)
Correct Answer: A,C
Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)
Correct Answer: C,D,E
Which of the following statements regarding ATP checks in SAP ECC that are triggered from customer orders is correct?
Correct Answer: B
You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you should be able to use a second sequence on other work centers for operations 30 and 40.
What sequence category do you use to create the second sequence in the system?
Correct Answer: C
You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).
Which of the following statements is true for the resulting dependent requirements?
Correct Answer: A