ISTQB Certified Tester Advanced Level - Test Manager - CTAL-TM Exam Practice Test
You have been carefully monitoring the progress of testing for your project. You have been using the established traceability to verify that the requirements and test conditions are being adequately addressed. The test team is proceeding well in their test case execution and you can see that you are achieving about 80% coverage of the test conditions per the traceability mapping in your test management system. You have seen a number of defects being logged against test conditions that are failing, but you do not see a mapping of the test cases to those conditions.
What is likely to be occurring in the testing area that is causing the traceability to break down? [2]
What is likely to be occurring in the testing area that is causing the traceability to break down? [2]
Correct Answer: A
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.

Given this information what should you conclude?

Given this information what should you conclude?
Correct Answer: B
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
Which of the following is MOST likely to influence the choice of test levels for a project?
Correct Answer: A
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.
Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.
Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]
Correct Answer: B
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
Which of the following software characteristics are possibly revealed through the application of a open source static analysis tool?
Correct Answer: D
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
You are preparing the estimate for the test plan, which should cover all test activities subsequent to the plan having been agreed. Estimation of test activities has in the past been embarrassingly inaccurate. Historical data from previous similar projects is unreliable, but for two recent projects it is possible to find out how many test cases were developed and how long this took.
Which TWO of the following estimation techniques will be BEST in this scenario?
Which TWO of the following estimation techniques will be BEST in this scenario?
Correct Answer: B,C
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority
/severity defects, 100% pass rate for all test cases covering risks that are classified as
"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.
Given this information, which lifecycle model should you recommend? [3]
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of delivered product and will be watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority
/severity defects, 100% pass rate for all test cases covering risks that are classified as
"high" or "very high", 90% pass rate for all "medium" risks and 50% pass rate for all "low" and "very low" risks.
Given this information, which lifecycle model should you recommend? [3]
Correct Answer: B
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
Which of the following Is the common set of information to be produced in a test estimate''
Correct Answer: D
Explanation: Only visible for ExamsLabs members. You can sign-up / login (it's free).
A test team is working long hours to achieve a deadline for release of a new product which has had problems throughout development and is well behind schedule. Which of the following is most likely to have a MOTIVATING effect on the testers in the team?
SELECT ONE OPTION
SELECT ONE OPTION
Correct Answer: A