Microsoft Managing Programs and Projects with Project Server 2013 - 74-344 Exam Practice Test

Your organization uses Project Online for project portfolio selection. The business drivers and priorities are set, as are the main constraints to identify the efficient frontier.
The company has been collecting business cases for new proposals in which many projects may solve the same business need. For example, the selection for a Customer Relationship Management system has six different proposals, whereas only one is necessary to fulfill the business need.
You need to guarantee that the analysis will produce the most viable proposal in terms of cost and resources and that no repetitive efforts exist in the portfolio selection.
What should you do?
Correct Answer: B
You are an administrator in an organization that uses Project Server 2013. Single entry mode is disabled.
Resources use the Tasks page in Project Web App (PWA) to report task progress. You need to ensure that resources have the ability to report work actuals per day.
What should you do?
Correct Answer: C
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.
You review your organization's issue management process.
You need to implement a new issue management process that meets the following requirements:
--
All issues for future projects need to be associated with a source. Source values are either Internal or External.
What should you do?
Correct Answer: C
Your organization uses Project Server 2013. For security reasons, only individuals inside your organization have access to Project Web App (PWA).
You want to keep track of progress made by a third-party vendor. The vendor will email task progress to the resource manager. The resource manager will be responsible for reporting vendor progress back to the project manager in PWA.
You need to enable this functionality.
You add the vendor as a resource in Project Server.
What should you do next?
Correct Answer: D
You are a project manager in an organization that uses Project Server 2013. Single-entry mode is disabled. The Only allow task updates via Tasks and Timesheets option is enabled.
Project team members submit updates to tasks through Project Web App (PWA).
A team member submits a status update to you for approval. The team member later
informs you that they made a typing mistake in the status update.
You need to correct the status update.
What should you do?
Correct Answer: D
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Project Site Provisioning Mode for your organization allows users to choose when to provision project sites.
You use Project Web App (PWA) to create a new enterprise project named Sub1 that will be inserted as a subproject in your existing master project named Master.
You need to create a new project site for Sub1 as a subsite of the existing Master Project Site.
What should you do?
Correct Answer: B
You are a program manager for an organization that uses Project Server 2013.
You are responsible for implementing a data warehouse that compiles relational data from many business areas. Your project managers need to be able to manage the implementation for a business area as separate projects, while still recognizing the dependencies at a program level.
You need to maintain ownership and authority of key program dates at the program level.
What should you do?
Correct Answer: C
You are a project manager in an organization that uses Project Server 2013. You manage two projects named Proj1 and Proj2.
You create a deliverable dependency between both projects by taking the following actions:
- You create a deliverable named Deliverable1 against a milestone named Milestone1 in Proj1. The Finish date for Milestone1 and the Deliverable Finish date for Deliverable1 are the same.
- On Proj2, you associate a dependency that has a milestone named Milestone2 to the Deliverable1.
After several days of work, Proj1 has been rescheduled, which moves the Finish date for Milestone1 ahead by five days.
You need to ensure that these changes are reflected in both projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: B,D
You are a project manager who uses Project Server 2013.
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?
Correct Answer: C
You are a project manager for an organization that uses Project Server 2013. When you publish a new schedule, a default Project Site is created for you.
A team member asks you to create a task list separately from the schedule. The team member wants to use the list for specific work they need to perform in order to complete one of the assignments in the project schedule.
On your Project Site, you have the tasks that they have asked for in a task list. The work being performed by this team member becomes critical to the success of your overall schedule.
Management asks for a simple report showing them the task list in an easy-to-read format.
You need to implement this request.
What should you do?
Correct Answer: A