Cisco Certified Design Expert Practical - 352-011 Exam Practice Test

As part of network design, two geographically separated data centers must be interconnected using Ethernet-over-MPLS pseudowire. The link between the sites is stable, the topology has no apparent loops, and the root bridges for the respective VLANs are stable and unchanging. Which aspect must be the part of the design to mitigate the risk of connectivity issues between the data centers?
Correct Answer: A
A financial trading organization plans to monitor the network latency for multicast data feeds on a hop-by-hop basis. Which technology should be added to their design to support this requirement?
Correct Answer: D
Which two control plane policer design options should you consider to achieve high availability? (Choose two)
Correct Answer: A,B
Which MPLS attribute is required for links to carry a given MPLSTE tunnel?
Correct Answer: C
Which native mechanism does OSPF use to prevent loops in MPLS VPNs?
Correct Answer: E
What are two possible drawbacks of ending Loop-Free Alternate to support fast convergence for most destination IGP prefixes? (Choose two)
Correct Answer: B,C
What is an implication of using route reflectors in an iBGP topology?
Correct Answer: B
Which two reasons for implementing Cisco MPLS TE in a service provider MPLS backbone are valid?
(Choose two.)
Correct Answer: B,C
You are designing a WAN network solution with EIGRP based on VPLS. The interface speed is 10Mb/s, but the access rate of the WAN connection is 256 Kb/s. What should you include in the network design, in order to avoid potential issues with EIGRP?
Correct Answer: D
As a part of a network design, you should tighten security to prevent man-in-the-middle. Which two security options ensure that authorized ARP responses take place according to know IP-to-MAC address mapping?
(Choose two)
Correct Answer: B,E
As network designer, which option is your main concern with regards to virtualizing multiple network zones into a single hardware device?
Correct Answer: B
Refer to the exhibit.

How should you redesign this network running BGP to improve availability of the routers 1A and 1B at the core site?
Correct Answer: C
You must make IGP redesign recommendations for a client that has old equipment, with low CPU power and memory, that they do not have budget replace. They are very concerned about CPU load on routers. They are using IS-IS as the IGP in a single l1 area and all routers are connected to each other with point-to-point links.
Which method do you recommend to reduce or limit CPU overhead caused by IS-IS?
Correct Answer: D
An enterprise customer has a national WAN network based on DMVPN over the Internet, with sites located throughout the country. The customer has recently deployed VoIP throughout the entire network , and users report that it takes up to 2 seconds to establish a telephone call to an IP telephone at another office network.
Drag and drop the root cause and the corresponding design solution from the left onto the correct targets on the right Not all options are used
Correct Answer:

Explanation
DMVPN spoke to spoke tunnels take a few second
Use DMVPN to set up tunnels and GETVPN for encryption