Oracle Project Management Cloud 2025 Implementation Professional - Delta - 1D0-1057-25-D Exam Practice Test

When implementing Project Performance Reporting, your customer has the following requirements:
Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition?
(Choose the best answer.)
Correct Answer: A
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?
Correct Answer: C
Which three are part of using the Rapid Implementation for Project Financial Management Applications macro-enabled Microsoft Excel spreadsheet to enter setup data?
Correct Answer: B,D,E
Your client is involved in automation control systems installation.
Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a I O spread point scale resembles:
0-4-10-11-14-13-10-4-0-0. Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two}
Correct Answer: A,C
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance 100%
After approval, the PO is closed for without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the
"Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that is no Cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
Correct Answer: A,C
Which three features are part of Oracle Fusion Functional Setup Manager?
Correct Answer: A,C,D
Which three setups can be configured by using Rapid Implementation for Project Financial Management Applications?
Correct Answer: A,B,C