A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,D
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: C
Which advanced functionality has been embedded in SAP S/4HANA?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,E
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,E
What are the three transition scenarios for an S/4HANA implementation?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
How can Production Planning and Detailed Scheduling (PP/DS) enhance the standard planning functionality?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: A
When would you use reporting point backflush in repetitive manufacturing?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
You are using the document management system (DMS) . Where should the DMS document links be assigned, to have them automatically copied to production orders?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
The setup time on the production line to produce a material is extensive. You would like to avoid multiple setups and limit the production of the material based on a planning calendar.
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
Correct Answer: B
What are attributes of the SAP S/4HANA Simplification list?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D