Oracle Manufacturing Cloud 2017 Implementation Essentials - 1z1-348 Exam Practice Test
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
Correct Answer: D
A user wants to transfer the work order status updates and resource transaction data for costed resources to Cost Management.
Which scheduled process should you run to achieve this requirement?
Which scheduled process should you run to achieve this requirement?
Correct Answer: C
Your customer is a light assembly manufacturing company that doesn't require shop floor control. A manufacturing engineer wants to generate a work definition automatically for some items, and wants to eliminate the explicit maintenance of work definitions.
Which three steps must be completed and verified in the Work Definition area?
Which three steps must be completed and verified in the Work Definition area?
Correct Answer: C,D,E
In a manufacturing plant, a production operator in a given shift completes a car assembly and reports this using orderless completion by referencing a Work Definition.
Identify the two purposes of the referenced Work Definition in Orderless reporting.
Identify the two purposes of the referenced Work Definition in Orderless reporting.
Correct Answer: A,D
You can generate and manage work order exceptions in Oracle Manufacturing Cloud.
Which users can report production exception and who gets notified after an exception is raised?
Which users can report production exception and who gets notified after an exception is raised?
Correct Answer: C
Identify the two capabilities that the Application Development Framework Desktop Integration (ADFDI) framework provides for Work Definitions in Manufacturing Cloud.
Correct Answer: B,D
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the Morning Shift and the remaining units are available for the Evening Shits.
Which two actions must you perform to associate LATHE with W1?
Which two actions must you perform to associate LATHE with W1?
Correct Answer: A,C